  • Underground work for our road resurfacing project will begin Wed 09/04/2024.
  • Culvert and ditch work should take about 3 days each
  • Culvert work on N. Circle and Park Dr. begins Wednesday, 9/4/24
  • Tree service will be out before Wednesday to remove 3 trees on N Circle (marked)
  • Manhard will be onsite to monitor & answer resident questions.
  • Locations, driveway culverts
    • 11 N Circle, 24 N Circle,  64 N Circle, and 116 Park. 
  • Locations, Storm Sewer Road Crossings
    • 138 Park and 43 N Circle.
    • Road Repair & Resurfacing includes:
      • N Circle Ave
      • Evergreen Ct
      • Park Drive
        • Boat Launch
      • Peninsula Ln (intersection @ Channel)
      • Channel Dr (Repairs @ Peninsula and the curve)