Road Project Begins 9/4/24
- Underground work for our road resurfacing project will begin Wed 09/04/2024.
- Culvert and ditch work should take about 3 days each
- Culvert work on N. Circle and Park Dr. begins Wednesday, 9/4/24
- Tree service will be out before Wednesday to remove 3 trees on N Circle (marked)
- Manhard will be onsite to monitor & answer resident questions.
- Locations, driveway culverts
- 11 N Circle, 24 N Circle, 64 N Circle, and 116 Park.
- Locations, Storm Sewer Road Crossings
- 138 Park and 43 N Circle.
- Road Repair & Resurfacing includes:
- N Circle Ave
- Evergreen Ct
- Park Drive
- Boat Launch
- Peninsula Ln (intersection @ Channel)
- Channel Dr (Repairs @ Peninsula and the curve)